What happens once the house arrives?
1. Laying Out The Site and Building the Foundation
Install temporary power and have electricity hooked up. Lay out site, install batter boards, dig foundation trenches and install the foundation forms. Pour footings, build foundation walls and piers, and install mud sills.
2. Setting House Units
Work crews lift components by crane onto the foundation.
3. Roofing
Install knee boards, collar ties and rafter supports. Install gable end walls, structure wood and supports. Install roof vents. Install roof underlayment and shingles on hinge rows. Install ridge cap shingles.
4. Dormers
If applicable, cut out roof, install dormer walls, trusses, roof decking, roof edge, tar paper, roll roofing in valleys, install shingles, metal flashing on front wall, install windows and finish trim.
5. Exterior
Complete installation of exterior siding and trim, soffit and fascia. install windows in gable ends. Paint exterior doors and door jambs. Install shutters and optional exterior storm/security doors.